The magazine leStrade (Aeroporti Autostrade Ferrovie), Italy’s most authoritative technical magazine dedicated to transport infrastructure, chose to publish an in-depth article on Imeva’s cable solutions in its September 2020 issue (number 1560).
Below is the article by Pietro Varricchio, Global Business Developer at Imeva.
The steel structure of the pipelines
LET’S TAKE A CLOSER LOOK AT THE TECHNICAL FEATURES AND INSTALLATION METHODS OF ‘ESLAO’, THE STRUCTURAL ELEMENTS MADE OF CORRUGATED STEEL SHEET – FOR THE CONSTRUCTION OF LOAD-BEARING PIPES (CSP CORRUGATED STEEL PIPE) AND MORE – DEVELOPED AND MANUFACTURED BY IMEVA. KEY BENEFITS INCLUDE: REDUCED EARTHWORKS COMPARED TO CEMENT-BASED SOLUTIONS, AS WELL AS RAPID INSTALLATION IN CASES WHERE ROAD ACCESS NEEDS TO BE RESTORED.
As part of its manufacturing programme, IMEVA produces various types of elements known as ESLAO, which stands for ‘Elementi Strutturali in Lamiera di Acciaio Ondulata’ (Structural Elements in Corrugated Steel Sheet), whose main use is in the construction of Corrugated Steel Pipes (CSP) in the road construction sector. Subjected to road traffic loads (weight of the embankment, dynamic action between moving loads in transit, seismic action, etc.), an ESLAO load-bearing pipe, being highly elastic, tends to deflect in height, bulging at the sides each time a vehicle passes over it. This tendency, adequately counteracted by the surrounding soil – which is therefore required to perform a truly static function – gives the “pipe-soil” system extremely high stability, as well as considerable load-bearing capacity and long-life performance.
Tipologie di elementi
ESLAO, suitably shaped, allow for the creation of various types of load-bearing conduits, including circular, lowered, underpass and arched sections. IMEVA’s standard ESLAO products have increasing wave widths and thicknesses depending on the size of the load-bearing conduit to be created. In detail:
Small pipes, for example with a diameter/clearance between:
• 0.50 m and 1.80 m: these can be conveniently made using ESLAO wave pitch 70, wall thicknesses from 1.5 mm to 2.5 mm;
• 0.80 m and 2.80 m: these can be conveniently constructed using ESLAO wave pitch 100, wall thicknesses from 1.5 mm to 3.5 mm;
Medium/large conduits, for example with a diameter/span between:
• 2.00 m and 7.00 m – can be conveniently constructed using ESLAO with a wave pitch of 150 and wall thicknesses from a minimum of 2.5 mm to a maximum of 7.0 mm;
• 2.00 m and 9.00 m – can be conveniently constructed using ESLAO wave pitch 200, wall thicknesses from min. 2.5 mm to max. 7.0 mm.
Each supply comes with its own assembly diagram showing how to insert the various ESLAOs.
Nel vivo dell’installazione
On-site assembly requires a suitable lifting and transport vehicle, such as a mobile crane, for positioning the ESLAOs at height, and very minimal additional equipment, such as:
- Maniglioni per il prelievo dell’ESLAO dal relativo collo e l’aggancio al bozzello dell’autogru;
- Spine coniche per l’allineamento in quota degli ESLAO;
- Ponteggio mobile – da allestire interno della condotta – per le operazioni di inserimento ESLAO e relativa bulloneria;
- Avvitatori pneumatici od elettrici per il mutuo serraggio degli ESLAO.
The installation of a steel load-bearing conduit therefore requires simple mechanical assembly and earthmoving work: this makes the use of this system particularly advantageous in terms of cost and time compared to traditional reinforced concrete structures. In unfavourable weather conditions and/or emergencies, when, for example, immediate action is required to restore traffic interrupted by an accident, the lightness and elasticity of the system make it absolutely irreplaceable. In the event of settlement and subsidence of
road embankments, the ESLAO conduit tends to follow the movements without fracturing or losing its functionality.
The installation procedure involves creating a laying surface, normally consisting of a layer of granular inert material, rolled and compacted, on which the ESLAO pipes are laid and assembled. Backfilling is then carried out, gradually adding layers of soil in uniform layers – normally around 30 cm high – on either side of the pipe, so that the backfill level advances in parallel. Each layer of backfill is individually and carefully compacted: with hand tampers near the part below the metal pipe and immediately around it; with mechanical means, jumping rings, vibrating plates and road rollers for the remaining part.
A special case is the backfilling of arches, for which the various layers of backfill are progressively adapted to the shape of the structure: by loading on one side only, the arch may deform towards the opposite side; by loading on the sides in horizontal layers, a key deformation may occur.
When installing arched structures, a special reinforced concrete foundation must be built, suitably sized to distribute the loads to the subgrade. In the case of ‘multiple’ installations, i.e. several structures to be placed side by side in parallel, adequate spacing between them is required; this ensures an even distribution of forces on the sides and facilitates the backfilling process. The heads are often finished with a ‘beak’ cut according to the slope of the embankment (normally 2:3), or with head walls made of stone, concrete or steel.
Iniziative speciali
ESLAO is also frequently used in the manufacture of special components for general construction systems.
In the plant engineering sector, ESLAO is often used in the construction of inert storage stations in the form of large silos. When inert material is removed from the tongue using a special loading shovel (usually a rubber-tyred type), it extends to continuously feed the station itself. ESLAO is also frequently used in the construction of tunnels to protect plant networks in general.